Civil works complete at Woodman Point - Integrate Alliance has reached a major milestone on the Woodman Point Water Resource Recovery Facility Upgrade with civil works now complete.
Across the project to date, the team has delivered:
▪️ 7,950 m³ of concrete poured
▪️ 1,200 tonnes of steel reinforcement installed
▪️ ~29 km of underground conduit installed
▪️ 140 electrical pits installed
▪️ ~6 km of underground HDPE piping installed
Behind these numbers is a significant team effort, with concrete subcontractor TNE Civil reaching a peak of 45 people on site during the concrete works phase, while earthworks subcontractor Halo Civil Engineering had 43 people on site at peak.
Congratulations to everyone involved in reaching this important milestone. The project team’s hard work, collaboration and focus on delivery have helped bring the civil works phase to completion. Another step forward at Woodman Point!
Once compete, Woodman Point WRRF will support almost 900,000 people across Perth and set a new benchmark for sustainable infrastructure as WA continues to grow.
Ends -