Major progress on Suburban Rail Loop East!


The Terra Verde Joint Venture team has successfully completed piling works at Glen Waverley! The team installed 268 piles:
▪️ Each ranging 1,050mm – 1,180mm in diameter
▪️ Depths ranging from 16m to 34m
▪️ Overall, 6,200m³ of concrete was used

The team has since moved on to capping beam construction and commissioning of the permanent water treatment plant.

At Mount Waverley, the second row of ground anchors has been completed, while the acoustic shed frame and roof have been successfully installed, incorporating 170 tonnes of steel. Excavation continues to progress well, reaching 8.7m below the capping beam, alongside ongoing ground anchor installation.

Webuild, as part of the Terra Verde Joint Venture, is delivering almost 10 kilometres of parallel tunnels between the future Box Hill and Glen Waverley stations, along with 39 cross passages, two station boxes, two TBM launch sites, and an intervention and ventilation shaft for the Suburban Rail Loop East Project.

Ends -