Milestone month at SRL East’s Burwood site! Over the month of September, the team in Burwood successfully launched the first TBM, commissioned the conveyor system and installed the first tunnel rings. Strong progress was also achieved across the civils scope, including completion of the second level of struts at the Northern Tunnel Access Shaft (NTAS), the first pour of the NTAS acoustic shed slab, and excavation of the station box mezzanine.

Progress to date in numbers:
▪️ ~8,500m³ of concrete placed
▪️ 215,000 tonnes of spoil excavated, 
▪️ 42,000 tonnes of crushed rock installed and 
▪️ 1,080 tonnes of reinforcing steel installed 

With commissioning of the second TBM progressing, momentum continues to build across the site.

Webuild, as part of the Terra Verde Joint Venture, is delivering almost 10 kilometres of parallel tunnels between the future Box Hill and Glen Waverley stations, along with 39 cross passages, two station boxes, two TBM launch sites, and an intervention and ventilation shaft for the Suburban Rail Loop East Project.

Ends -