First major concrete pour at Osborne Park Hospital Expansion complete!
Construction at the Osborne Park Hospital expansion is in full swing with the first structural concrete pour taking place on site.
The core 3 raft slab concrete pour reinforces the foundation, which will support part of the structure, providing the strength and stability needed from the ground up.
The milestone involved 130 tonnes of reinforced steel, 500 cubic metres of concrete and 85 concrete trucks, with the pour completed over nine hours.
Planning for a much larger concrete pour at the site is under way and expected to take place in the coming week.
Webuild is proud to be safely delivering the New Women and Babies Hospital Project, which will support the Western Australian community for generations to come.
Ends -