Powering ahead at North East Link - The Spark North East Link Tunnels D&C team is making huge progress, with the Tunnel Boring Machines (TBMs) now over 3.5km ahead on their tunnelling journey.
Since the start of tunnelling, the TBMs have laid close to 31,000 segments as they work their way towards Bulleen.
Backend works are also progressing well with the team now past the halfway point of cross passage excavation.
Read more about North East Link here.