Progress is taking shape at North East Link!


The Spark North East Link Tunnels D&C team continues to make strong progress at the Lower Plenty Road site, with roof slabs being installed over the northbound and southbound tunnels.

Check out the time-lapse video here.
 
Since June, 173 roof beams have been installed, helping close sections of the tunnel box. With a total of 384 roof beams to be installed, around 90% are expected to be in place by the end of the year.
 
Looking ahead, this area will be transformed into Borlase Reserve upon project completion in 2028, creating a new nature and habitat corridor featuring wetlands, walking paths, playgrounds and open community spaces.
 
We're proud to be contributing to a project that is creating lasting benefits for future generations.
 
Webuild, as part of the Spark Joint Venture, is delivering North East Link. The project will take up to15,000 trucks off local roads every day and reduce travel times by up to 35 minutes for commuters. Once complete, it will be the longest road tunnel in Victoria.